January 1st, 2007 by Frederick | Print

Nearing completion

Construction commenced in May 2006 and was substantially complete by November 2006, a time lapse of only six months. Credit for the achievement is due to Paolo, il capomastro. Paolo blends his knowledge of traditional construction techniques with an understanding of contemporary requirements and needs. He is also a very hard worker. The result has exceeded expectation.

 May 2006

 November 2006

Wood casement windows with insulation glass were installed in the restored openings. Simple wood interior and exterior doors appropriate to the structure were replicated except for a pair of glass doors providing access from the kitchen and dining area to the new veranda looking southwest to the Monti Sibillini. The final plaster finish was applied to the early 20th century addition. The stair to the entry portico was reinforced and restored.

   
   
   

Interior plasterwork was completed around restored window openings and tile sills were installed. Traditional floor tiles were laid on all floor surfaces and sealed. Masonry supports for kitchen and bathroom stone countertops were constructed and plastered.

   
Il soggiorno Il soggiorno
   
La sala da pranzo La camera da letto
   
 
La cucina  

 

2 Responses to “Restoration of a casa colonica.8”

  1. crispin Says:

    frederick you old diuvil  you never told me you were speaking to the world! should we all be public? the poet told me we should only speak to the initiated: favete linguis!l

  2. Sandra Says:

    An outstanding job!  Beautiful.

Leave a Reply